Dated: 28th July 2025
Source: Ministry of New & Renewable Energy (MNRE), Government of India
Subject: Implementation of ALMM List-II for Solar PV Cells.
1. Overview
The Ministry of New & Renewable Energy (MNRE) has issued an official amendment regarding the implementation of ALMM List-II for solar PV cells, effective from 1st June 2026. This marks a significant step to strengthen the quality and traceability of solar PV cells used in government-supported and regulated solar projects.
2. Highlights of the Amendment
Mandatory Use of ALMM List-II (Solar PV Cells):
3. Cut-Off Date:
The amendment defines the cut-off date as exactly one month from the date of publication of List-II.
Example:
· If List-II is published on 1st August 2025, then:
· Cut-off date = 1st September 2025
· Bids submitted after this date must comply with List-I and List-II.
· Exemption for Older Projects:
1. Net Metering & Open Access Projects
· Commissioned before 1st June 2026 → exempt from List-II
· Commissioned after 1st June 2026 → must use both List-I and List-II components
2. Thin-Film Technology Modules
· Modules manufactured in integrated ALMM-listed plants are considered compliant with List-II requirements.
3. Separate ALMM List-I(a)
· From 31st May 2022, a sub-list (ALMM List-I(a)) is maintained for modules using non-ALMM-listed cells.
· Applicable only for projects not covered under mandatory ALMM use.